CSC Steel Fabricate and install process equipment for CSC Steel cold rolled mill, Melaka MALAYSIA 2007
Siemens-Vai Fabricate and installation of process equipment and structures for Mycron Steel cold roll mill, Shah Alam MALAYSIA Nov 2007
Yung Kong Galv Fabricate and install process equipment and structure for Yung Kong Galvanizing plant, Kapar MALAYSIA 2007 - 2008
Ann Joo Steel Engineering design, fabricate and installation of billet transfer equipment for Ann Joo Steel, Prai MALAYSIA Apr 2009
Ann Joo Steel Fabricate, assembly and installation of bar lifter device for Ann Joo Steel rolling mill, Shah Alam MALAYSIA May 2009
Ann Joo Steel Supply and fabricate Electric Arc Furnace slag door water cooled panel for Steel Making Plant Ann Joo Steel MALAYSIA July 2009
Siemens VAI Supply and fabricate of process equipment for Bluescope Metal Coating line No.2, Cilegon INDONESIA Mar 2009
Mitsubishi-Hitachi Metal Supply and fabricate of clean tank, dirty tank and oil lubrication tank for Sendzimir Mill, Bahru Stainless, Pasir Gudang MALAYSIA Dec 2010
Mitsubishi-Hitachi Metal Supply and fabricate of Mill Hood for Sendzimir Mill, Bahru Stainless, Pasir Gudang MALAYSIA Mar 2011
CSC Steel Supply and fabricate of coil transfer car for CSC steel, Melaka Malaysia Apr 2012
Andritz AG Supply and fabricate 9 units of Supporting Ring structure for Acid Pickling Tank, Bahru Stainless Pasir Gudang MALAYSIA June 2016
Consolis Malaysia Sdn Bhd Fabrication Of Longi welding machine June 2016
Consolis Malaysia Sdn Bhd Fabrication of Expanding machine complete with expanding tools June 2016
Consolis Malaysia Sdn Bhd Supply and fabricate of casting trolley and transfer trolley July 2016
Consolis Malaysia Sdn Bhd Supply and delivery of Cylinder Tilting Table complete with hydraulic power pack August 2016
Consolis Malaysia Sdn Bhd Supply and delivery of Rotary trolley August 2016
Consolis Malaysia Sdn Bhd Supply and delivery of Transfer Table, welding Table and casting manifold August 2016
Consolis Malaysia Sdn Bhd Supply and delivery of wall crossing steel cylinder size ND3000 August 2016
Consolis Malaysia Sdn Bhd Supply and delivery of Flange ND3000 c/w M68 bolts, nuts & washers January 2017
Consolis Malaysia Sdn Bhd Supply and delivery of all sizes insulating flanges for SS316L on size ND25, ND100, ND150 & ND200 and S235JR flanges on size ND50, ND1000, ND2200 & ND2800 complete with SS316L & Zn-coated Hexagon bolt, nut & washer and FTFE insulating tube & washers July 2017
Andritz Metal Supply, fabricate & assembly of Annealing Furnace Exit Lift Roll Equipment door element c/w insulation work Nov 2017
PT. Bonna Indonesia Supply and fabricate 2 units of Cylinder Tilting Tables c/w hydraulic power units Dec 2017
PT. Bonna Indonesia Supply and fabricate 7 units of rotator Trolleys Dec 2017
Consolis Malaysia Sdn Bhd Supply and delivery of all sizes flanges for SS316L on size ND25, ND50 & ND100 and S235JR flanges on size ND50, ND250, ND1000, ND2100 & ND2800 for Melaka CCGT Power Plant Nov 2018
Kiswire Neptune Sdn Bhd Supply and delivery of Steel Reels type B2824A (Reel diameter size 2800mm) and type B3434C (Reel diameter size 3400mm) Dec 2018
Knauf Insulation Sdn Bhd Supply, fabricate & Installation of Specialty Equipment Nov 2019
Knauf Insulation Sdn Bhd Supply, fabricate & Installation of Oven Ducting Dec 2019
Knauf Insulation Sdn Bhd Supply & fabricate and support for melter stack, EP exhaust duct and Refiner ducting equipment Dec 2019
Knauf Insulation Sdn Bhd Supply & fabricate and support for admix, dust collection and stack Feb 2020